B.C. ordered to pay family of tubing accident victim $150K

Andrew Barrie and two others died in 2012 after they went over Cascade Falls while tubing

Eight years after her husband died in a tubing accident that took him and two others to their deaths at Cascade Falls near Christina Lake, Carol Barrie will finally receive some court-ordered financial compensation from the government of British Columbia, which a judge has found to have dragged its feet since she first filed a civil suit against the province in 2014.

In an April 9, 2020 ruling, Justice Joel Groves of the Supreme Court of British Columbia ordered the province of B.C. to pay Barrie $150,000 to partially compensate her for provable loss and for legal fees spent thus far, as the province has repeatedly forced trial dates to be postponed.

Barrie’s husband Andrew and Christina Lake residents Ronald and Jacqueline Legare died on July 28, 2012, when they were tubing with a larger group down the Kettle River from Gilpin Grasslands Provincial Park. Barrie’s son first reportedly saw the Legares get swept away near the Great Trail’s trestle bridge at Cascade, before managing to save himself and his mother. Andrew Barrie’s body was recovered from the river seven days later, approximately a kilometre downstream.

Barrie’s initial suit, filed on behalf of herself and her children, names as defendants the province, the Regional District of Kootenay Boundary (RDKB), the City of Grand Forks, as well as the Legare estate and fellow tubers Scott MacNeill, Kathy MacNeill, Jacqueline MacNeill and Jamie MacNeill, whom Barrie’s claim alleges should have known of the danger of Cascade Falls. Nevertheless, the court determined in January that liability lays with the province.

Barrie’s suit argues that the province ought to be responsible for warning signage along the Kettle River, leading up to dangerous sections such as Cascade Falls.

No trial in 10 years

The interim compensation, called a tort advance, was ordered by Groves in April to “partially compensate a plaintiff for their provable loss and is designed to ensure that the costs associated with a delay in having the matter effectively resolved are not too onerous for an aggrieved plaintiff.”

The case’s first trial date was set for 2016, but both parties agreed to postpone. Groves blamed the province’s inaction and mishandling of the evidence disclosure process for subsequent delays, in 2018 and more recently in April 2020.

Because B.C. appealed Groves’ January ruling that laid liability for the case on the province, April’s trial was cancelled too. Though Groves noted that COVID-19 pandemic would have delayed the April date anyways, because the province appealed in February, they are still on the hook, he said. The judge said that the matter would likely not come to trial again until 2022 – 10 years after Andrew Barrie and the Legares died.

Provincial delays pile up

In his April 9 ruling, Groves said that both the adjournments in 2018 and 2020 can be blamed on the conduct of the province. “Both relate to their failure to follow the Civil Rules in regards to disclosure of documents,” he wrote.

Before the 2018 trial date, the province apparently failed to offer a full disclosure of relevant documents, despite staff having twice sworn affidavits insisting that they had disclosed everything. In B.C., unlike some other jurisdictions, sworn affidavits of disclosure from parties aren’t necessary, but can be requested by a judge when they believe that “a party needs to be reminded of the significance of their obligation and needs to be reminded that consequences can flow from the failure of that obligation to disclose documents,” Groves wrote.

Barrie’s counsel was able to unearth more than 42,000 government documents deemed relevant to the case that were not shared by the province – many of which Groves said could be found in simple Google searches.

Beyond the documents, Barrie’s counsel also noted that the province offered a representative without sufficient knowledge to go through the discovery process. The provincial representative was from Recreation Sites and Trails BC (RSTBC), and reportedly said in his March 11, 2016 discovery session that “The [Barrie] incident on the river fell outside of our specific area of responsibility.” Instead, the RSTBC representative placed that responsibility on BC Parks.

Seeking compensation for six years of legal action, Barrie asked the court last summer to be awarded a $250,000 tort advance – approximately 30 per cent of what Andrew Barrie would have earned between 2012 and 2020. Groves had denied the request as recently as January, when it appeared that a trial was immanent. When the province appealed his January decision to lay liability at their feet, he re-evaluated.

From Barrie’s original ask for a $250,000 tort advance, Groves noted that “She described circumstances which I consider to be hardship, circumstances that she has faced since the loss of her husband and the loss of his income to support their family,” adding that the evidence in her case was “significant.”

Still, $250,000 is well above what is usually awarded in a tort advance, Groves explained in his April decision, before settling on the $150,000 figure. Groves said in his decision that the evidence he’s seen so far “suggests a quantified loss well in excess of the requested tort advance.”

Read more: Legare couple from Christina Lake deceased after Kettle River tubing accident

Read more: Family suing over drowning


@jensenedw
Jensen.edwards@grandforksgazette.ca

Like us on Facebook and follow us on Twitter.

Grand Forkslawsuit

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

“Skeena,” by John Hudson and Paul Hanslow is one of five fonts in the running to become the default for Microsoft systems and Office programs. (Black Press Media File Photo)
Font named after Skeena River could become the next Microsoft default

One of the five new fonts will replace Calibri, which has been Microsoft’s default since 2007

FILE – Residents of the Kahnawake Mohawk Territory southwest of Montreal continue to monitor a blockade leading to blocked railroad tracks that pass through their community as they protest in support of Wet’suwet’en hereditary chiefs on Sunday, March 1, 2020. THE CANADIAN PRESS/Peter McCabe
B.C. Supreme Court rejects Wet’suwet’en bid to toss LNG pipeline certificate

Opposition last year by Wet’suwet’en hereditary chiefs set off Canada-wide rail blockades

B.C.’s public health restrictions on non-essential travel are reinforced by orders effective April 23, 2021 to stay within your own regional health authority except for essential travel such as work and medical appointmens. (B.C. government)
B.C.’s COVID-19 non-essential travel ban takes effect, $575 fines approved

Checks on highways, ferries between Lower Mainland, Vancouver Island, Interior

Protesters attempt to stop clear-cutting of old-growth trees in Fairy Creek near Port Renfrew. (Will O’Connell photo)
VIDEO: Workers, activists clash at site of Vancouver Island logging operation

Forest license holders asking for independent investigation into incident

Starting Tuesday, May 11, B.C. adults born in 1981 and earlier will be able to register for a vaccine dose. (Haley Ritchie/Black Press Media)
BC adults 40+ eligible to book COVID-19 vaccinations next week

Starting Tuesday, people born in 1981 and earlier will be able to schedule their inoculation against the virus

Parks Canada and Tla-o-qui-aht Tribal Parks dig the washed up Princess M out from sand along the south shore of the Pacific Rim National Park Reserve. (Nora O’Malley photo)
Rescue attempt costs man his boat off Pacific Rim National Park Reserve

Coast Guard response questioned after volunteer responder’s speedboat capsizes in heavy swells

Al Kowalko shows off the province’s first electric school bus, running kids to three elementary and two secondary schools on the West Shore. (Zoe Ducklow/News Staff)
B.C.’s first electric school bus making the rounds in Victoria suburbs

No emissions, no fuel costs and less maintenance will offset the $750K upfront expense

Road sign on Highway 1 west of Hope warns drivers of COVID-19 essential travel road checks on the highways into the B.C. Interior. (Jessica Peters/Chilliwack Progress)
B.C. residents want travel checks at Alberta border, MLA says

Police road checks in place at highways out of Vancouver area

Victoria police say the photo they circulated of an alleged cat thief was actually a woman taking her own cat to the vet. (Black Press Media File Photo)
Photo of suspected cat thief released by Victoria police actually just woman with her pet

Police learned the she didn’t steal Penelope the cat, and was actually taking her cat to the vet

Join Black Press Media and Do Some Good
Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

The Canadian Coast Guard icebreaker Louis S. St-Laurent sails past a iceberg in Lancaster Sound, Friday, July 11, 2008. The federal government is expected to end nearly two years of mystery today and reveal its plan to build a new, long overdue heavy icebreaker for the Canadian Coast Guard. THE CANADIAN PRESS/Jonathan Hayward
Vancouver, Quebec shipyards to each get new heavy icebreaker, cost remains a mystery

Vancouver’s Seaspan Shipyards and Quebec-based Chantier Davie will each build an icebreaker for the coast guard

Most Read