BC Hydro doing good job managing billions in capital assets, says auditor

However, audit did not examine $10.7-billion Site C dam, under construction in northeast B.C.

A report by B.C.’s auditor general says BC Hydro is doing a good job managing the province’s dams, generating stations and power lines.

Carol Bellringer says in the audit that BC Hydro’s assets are valued at more than $25 billion and even though some generating facilities are more than 85 years old, they continue to operate near full capacity.

The report says about 80 per cent of Hydro’s assets are dams, generators, power lines, poles, substations and transformers that are used to provide electrical service to B.C.

READ MORE: Former B.C. Hydro CEO earns half a million without working single day

The audit says Hydro invested almost $2.5 billion to renew, repair or replace the assets it manages during the last fiscal year, ending March 31, 2018.

Bellringer’s audit does not examine the $10.7 billion Site C dam project, which is currently under construction in northeast B.C. and not slated for completion until 2024.

She says the audit examined whether BC Hydro has the information, practices, processes and systems needed to support good asset management.

The Canadian Press

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Stop checks, searches of Wet’suwet’en pipeline opposers unlawful: Watchdog

Wet’suwet’en hereditary chiefs, the B.C. Civil Liberties Association, Union of B.C. Indian Chiefs file complaint

Wet’suwet’en pipeline supporters speak up

“Protesters get one side of the story and they stand up with their fists in the air.”

Bachrach rejects calls for police action against demonstrators

Skeena-Bulkley Valley MP says only way out of crisis is “true nation-to-nation” talks

Coast Mountain College appoints a new president

The promotion came from within the school

Coastal GasLink pipeline investor committed to closing deal despite protests

Developer TC Energy Corp. — formerly TransCanada Corp. — is to remain the operator of the $6.6-billion pipeline

Blair says RCMP have met Wet’suwet’en conditions, calls for end to blockades

The Wet’suwet’en’s hereditary chiefs oppose the Coastal GasLink project

Petition seeks to remove local police department from Lindsay Buziak murder case

American woman starts online petition in hopes of helping Buziak family

Health officials confirm sixth COVID-19 case in B.C.

Woman remains in isolation as Fraser Health officials investigate

Study says flu vaccine protected most people during unusual influenza season

Test-negative method was pioneered by the BC Centre for Disease Control in 2004

Saskatchewan and B.C. reach championship round at Scotties

British Columbia’s Corryn Brown locked up the last berth in Pool B

B.C. lawyer, professor look to piloting a mental-health court

In November, Nova Scotia’s mental-health court program marked 10 years of existence

COLUMN: Not an expert on First Nations government structures? Then maybe you should calm down

Consider your knowledge about First Nations governance structures before getting really, really mad

One dead in multi-vehicle collision involving logging truck on northern B.C. highway

DriveBC says highway expected to remain closed until 8 p.m.

B.C. teacher gets 15-year ban after lying about having sex with just-graduated student

Teacher had been dishonest with the B.C. Commissioner for Teacher Regulation

Most Read