Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepencies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Just Posted

Wind project between Haida Gwaii and Prince Rupert moves forward once more

Naikun Wind Energy Group announced partnership with major offshore wind development company

Adverse weather forces ferry schedule change

Thursday’s Skidegate to Prince Rupert route affected

Coast Mountain College announces interim president

Ken Burt, current president and CEO, will say goodbye to CMNT come September

Queen Charlotte crackdown

RCMP target impaired driving amidst rising numbers of the offence

Australian gold mining giant acquires Red Chris mine

Newcrest now owns 70 per cent of the mine south of Iskut and operatorship

VIDEO: B.C. woman meets biological mother, 38 years later

Mother never gave up hope of finding daughter, despite all the obstacles

B.C. VIEWS: Pipelines set to roll as federal politicians posture

Projects to drive B.C., Canadian economy in years ahead

B.C. Lions fall to 1-9 after 13-10 loss to Ticats

Lowly Leos have dropped six straight CFL contests

VIDEO: B.C. woman meets biological mother, 38 years later

Mother never gave up hope of finding daughter, despite all the obstacles

B.C. man who died after rescuing swimmer was known for helping others

Shaun Nugent described as a dad, a coach, a hero and ‘stand-up guy’ at celebration of life

B.C. RCMP plane chases fleeing helicopter as part of major cross-border drug bust

The helicopter eventually landed at a rural property near Chilliwack

Thousands cycle to conquer cancer

The 11th annual Ride to Conquer Cancer took place Saturday morning, Aug. 24 in Surrey, B.C.

PHOTOS: Brazil military begins operations to fight Amazon fires

Amazon fires have become a global issue, escalating tensions between Brazil and European countries

Racist confrontation in Richmond parking lot caught on camera

Woman can be heard yelling racial slurs, swear words at woman in apparent parking dispute

Most Read