New power line needed for LNG project

Would connect Site C to LNG plant at Kitimat

BC Hydro is dusting off plans first proposed years ago to build a power line to Kitimat to service Kitimat LNG should a positive Final Investment Decision be announced.

Kitimat LNG wants to use electricity from BC Hydro instead of natural gas to power its equipment to compress and super-cool natural gas for export overseas.

In using electricity instead of natural gas, Kitimat LNG — a partnership of Chevron and Australian-based Woodside Energy International — is being billed as a way to significantly reduce greenhouse gas emissions.

But Kitimat LNG would first need BC Hydro to build a transmission line to Kitimat – the current 287kv line which runs along the east side of the Kitimat River valley can only provide for BC Hydro’s existing requirements and the LNG Canada plant now under construction.

READ MORE: LNG Canada cost to exceed stated $40 billion price tag

“The proposed [Kitimat] LNG project would require additional capacity beyond that which is currently available in the region,” said BC Hydro official Kevin Aquino last week.

“As such, we’re currently assessing what the potential impact would be in terms of capacity and transmission.”

Aquino stopped short of indicating whether the amount of power needed by Kitimat LNG would come from BC Hydro’s massive Site C project now under construction in northeastern B.C.

“It’s important to note that our electricity system is integrated and does not pinpoint a single generation resource, such as a dam, to a single customer, like an LNG project.”

The electricity required to power the operations of Kitimat LNG would be supplied through our own integrated system,” said Aquino.

Details about how much power Kitimat LNG would need wasn’t provided.

“Customer load information is confidential and commercially sensitive,” Aquino said.

Renewed interest in the Kitimat LNG project surfaced earlier this month when joint venture partners Chevron Canada and Woodside submitted an application to the National Energy Board (NEB) to double the original export goals and extend the export licence from 20 years to 40 years, following a redesign of the original project first developed in the early part of the decade.

The redesign calls for the production of 18 million metric tonnes of liquefied natural gas a year from three “trains” or processing lines.

Natural gas would be pumped from northeastern B.C. through the already-approved but not-yet-started Pacific Trail Pipeline to the Kitimat LNG site at Bish Cove just outside of Kitimat.

There’s no indication of when Kitimat LNG might announce that it is proceeding with its project.

B.C. Hydro’s preparations to provide power to LNG plants at Kitimat were first revealed in 2012 via a document examining long-range requirements around the province.

The crown corporation listed Kitimat LNG, LNG Canada (which is already under construction) and a project since abandoned called BC LNG as potential customers.

READ MORE: Chevron seeks NEB licence that could nearly double production at Kitimat LNG

Then, as now, BC Hydro indicated the one existing 287kv line it has from the Skeena Substation just south of Terrace to the Minette Substation near Kitimat was incapable of handling all potential requirements.

The Skeena Substation is a regional distribution point for power coming into the area via a 500kv line from the Williston Substation near Prince George. A variety of other lines then branch out from the substation to communities around the region.

“One option for meeting these future needs is a new 500kv line linking Williston Substation to Minette Substation for an approximate length of 500 km,” explained the 2012 BC Hydro document in commenting on how it could serve LNG customers.

The Williston Substation is a key BC Hydro facility, serving as a connecting point for power coming from BC Hydro’s existing facilities in the northeast and from Site C when it’s completed.

Chevron Canada communications team lead Leif Sollid said that Kitimat LNG is in discussions with BC Hydro but could not disclose any information on power requirements for the plant at this time.

Just Posted

Terrace hospital’s business plan approved

Health Minister’s announcement opens door to construction phase

Convicted animal abuser to return to B.C. court May 21

Catherine Jessica Adams is facing a breach of probation charge

Concerns over democracy as Senate committee votes to nix oil tanker ban

Critics of the Senate’s recommendation to kill Bill C-48 say it goes against popular will

Northwest Fire Centre open burn ban lifted

Recent rain, cooler temperatures have lowered the region’s fire risk

Telkwa pot plant application passes review

Cannabis company claims new Health Canada regulations are working in its favour

Rescuers finally persuade Eiffel Tower climber to come down

The official said the man was ‘under control and out of danger’ on Monday night

Federal government funds millions to help B.C. police spot drugged driving

Many police departments have expressed wariness about using the only government-approved roadside test

Judge: Mississippi 6-week abortion ban ‘smacks of defiance’

The new law would prohibit most abortions once a fetal heartbeat can be detected

Oil companies, 24-cent gap between B.C., Alberta to be focus of gas price probe

Premier John Horgan called the spike in gas prices ‘alarming’

Motorcycle deaths spike 50% since 2017

Riders were most likely fatally crash on the weekends compared with the rest of the week

Mother of accused charged in death of Surrey teen girl found in torched SUV

Manjit Kaur Deo charged with ‘accessory after the fact’ in 2017 death of Surrey teen

Family of B.C. pilot killed in Honduras trying to ‘piece together’ tragedy

Patrick Forseth has a number of friends in the area and was loved by everyone

Justin Trudeau credits immigration for Canada’s growing tech sector

Trudeau stressed that Canada has become a major source of talent for tech all over the world

Feds launch tourism strategy designed to boost sector 25 per cent by 2025

The fund is supposed to back experiences that show off Canada’s strengths

Most Read